Photograph: Railway project workers at the Tunnel 10 breakthrough on November 27, 2026. Source: Ministry of Railways / PIB; institutional marks retained.
Sikkim’s first railway connection has moved past a major excavation milestone, but travellers should wait for an official opening and train-service announcement before planning a rail journey to Rangpo. Excavation is complete in all 14 tunnels of the Sivok–Rangpo project, the Ministry of Railways said on November 28.
The ministry’s announcement follows the November 27 breakthrough in Tunnel 10. At 5.3 km, it is the longest tunnel on the route. Teams worked from both ends and through two access tunnels before joining the excavation fronts.
What remains before trains can run
Tunnel lining, track laying and essential railway safety installations are among the remaining activities identified by the ministry. Excavation completion therefore marks an engineering stage, rather than the start of passenger operations. The release does not announce an opening date or a passenger timetable.
For residents, tourists and businesses in the region, that distinction is important: a construction milestone does not establish a bookable train service. Any journey should be based on a separately issued operational notice and timetable.
The route into Sikkim
The 45-km broad-gauge line passes through Darjeeling and Kalimpong in West Bengal and Pakyong in Sikkim. Tunnels account for approximately 86% of its length, reflecting the difficult Himalayan terrain. The project also includes 23 bridges.
The announced stations are Sivok, Riyang, Melli and Rangpo, with an underground halt at Teesta Bazaar. At Sivok, the route will join the existing New Jalpaiguri–Alipurduar railway line. The ministry expects the completed connection to support passenger travel, essential supplies, local markets and tourism; these are prospective benefits.