₹4,288-Crore Second Container Terminal Approved for Kamarajar Port

Container cranes at Chennai Port viewed across the sea from Marina in a 2011 file photograph.

File photo: Chennai Port container terminal viewed from Marina, 16 March 2011; a regional logistics image, not Kamarajar Port or its proposed new terminal. Photo: VtTN / Wikimedia Commons, CC BY 3.0. Resized and branded by NDR.

NEW DELHI, November 26: A proposed second container terminal at Kamarajar Port in Tamil Nadu has received central approval, with annual capacity planned at 2 million twenty-foot equivalent units. The Cabinet Committee on Economic Affairs cleared the ₹4,288.26-crore project, including GST, on November 25.

The official decision envisages a 900-metre terminal and an 18-metre design draft. The development is intended to serve export-import cargo from the Chennai–Ennore industrial region and the wider southern hinterland.

Two phases and separate dredging costs

The selected private concessionaire will arrange finance under a design, build, finance, operate and transfer model. Phase I carries an estimated cost of ₹2,429.32 crore for 1.1 million TEUs; Phase II adds 0.9 million TEUs at ₹1,858.94 crore.

Kamarajar Port Limited will separately bear an estimated ₹450 crore for dredging. That amount is additional to the private-partnership component. The Statesman’s report also distinguishes the two costs.

A TEU is a standard measure of container capacity based on a twenty-foot container. The proposed capacity is an annual handling figure, rather than the number of ships the terminal can receive.

Timelines depend on the concession award

The concession runs for 40 years, including construction. Phase I is targeted within 24 months of the concession award, with commercial operations from month 25. Full operations are envisaged from month 49 after the second phase.

These are project milestones measured from an award, not fixed calendar opening dates. Approval therefore does not mean the new terminal is already operating.

The existing terminal handled about 0.7 million TEUs against installed annual capacity of 0.8 million in FY 2025–26, the government says. The expansion is meant to provide additional room for regional trade.

More verified public-infrastructure developments appear in our National coverage.

Photo: File photo: Chennai Port container terminal viewed from Marina, 16 March 2011; a regional logistics image, not Kamarajar Port or its proposed new terminal. Photo: VtTN / Wikimedia Commons, CC BY 3.0. Resized and branded by NDR.